Client
Transgrid
Project duration
2023-2025
Delivery timeframe
Complete
  • Renewables
Enerven successfully delivered the 330kV switching station for the grid connection of the 350 MW Culcairn Solar Farm project north of Albury, facilitating the integration of renewable energy into the New South Wales electricity network.

The customer

Transgrid builds and maintains the largest transmission electricity network in Australia, providing the backbone of the National Electricity Market while supporting the transition to a cleaner energy future.

"The successful delivery of the Culcairn Solar Farm switching station and transmission interconnection underscores Enerven’s engineering and project execution strength in high-voltage renewable infrastructure," Transgrid.

The opportunity

The Culcairn Solar Farm project is a landmark renewable energy project that demonstrates Enerven’s capability in complex grid infrastructure with the end-to-end execution of a 330 kV interconnection.

Neon’s Culcairn Solar Farm project officially entered commissioning in mid‑2025. The 350 MW (440 MWp) solar energy project has energy output sufficient to power approximately 155,000 to 160,000 homes annually via renewable generation.

Enerven’s scope covered the full lifecycle of works, including the design, procurement, construction, testing, and commissioning of the switching station and interconnection structures linking the Culcairn Solar Farm to the existing 330 kV TL6Y transmission line. The project was delivered in stages, commencing with civil design for early works, followed by civil construction, high-voltage plant installation, and ultimately the commissioning of the completed assets.

The solution

Key specifications delivered by Enerven:

  • Design, procurement, construction, testing, and commissioning of the switching station and interconnection structures linking the Culcairn Solar Farm to the existing 330 kV TL6Y transmission line.
  • The project was delivered in stages, commencing with civil design for early works, followed by civil construction, high-voltage plant installation, and ultimately the commissioning of the completed assets.
  • Upon successful completion of SP1, our second major NSW transmission infrastructure project in NSW, Enerven has become a trusted partner for Transgrid.

Enerven’s successful delivery of the Culcairn Solar Farm switching station and transmission interconnection underscores its engineering and project execution strength in high-voltage renewable infrastructure. Partnering with Transgrid on the development underscores Enerven’s growing reputation as a trusted partner for high‑voltage transmission infrastructure in New South Wales.

Why Enerven?

Our experience in the market place, combined with the expertise and industry knowledge of our team, makes Enerven’s offering second to none – which is why industry leaders such as Electranet, Transgrid, AGL and BHP Billiton trust Enerven with their energy infrastructure assets.

We invest heavily in the best equipment and the professional development of our staff, which means we combine experience and history with innovation and technology to deliver solutions that address the evolving energy distribution requirements of the community.

With a strong supplier and partner network behind us, our highly skilled staff work closely with you to fully understand your specific needs and vision, and will tailor a solution to suit.

Delivering the highest standard of work in a safe and environmentally sustainable manner is our top priority, and we have an outstanding track record to prove it. We focus on building long-term relationships with our clients, we’re committed to working with you for the lifecycle of your project and beyond.

Find out how Enerven can help on your next project.